Industry has long objected to the use of lowest priced, technically acceptable procurement strategies for technical/professional services and complex solution procurements, and it now appears that DOD is moving away from this practice.

Narrowing the use of LPTA

Under Secretary of Defense for Acquisition, Technology and Logistics, Frank Kendall, issued a memorandum on March 4 to clear up confusion about when LPTA is appropriate as a source selection process. His memo states LPTA “has a clear, but limited place in the source selection best value continuum” and narrowly defines when LPTA is appropriate for DOD procurements. This memo signals a shift away from the LPTA source selection process.

Download a copy of Kendall’s memo titled, “Appropriate Use of Lowest Priced, Technically Acceptable Source Selection Process and Contract Type.”

According to Kendall, LPTA should only be used when procurements meet four specific conditions:

  1. The requirements are well defined;
  2. The risk of unsuccessful contract performance is minimal;
  3. Price is a significant factor in the source selection; and
  4. There is neither value, need, nor willingness to pay for higher performance.

For technical service and solution bids, I would argue that none of these four conditions can be met. In most technical bids, requirements cannot be defined to a standard of acceptability that is understood by government and industry and that can be expressed in terms of performance measures that can be evaluated on an acceptable/unacceptable basis. It is hard enough to define the work, let alone a pass/fail standard that can be applied in proposals. Generally, the risk of failure in technical bids is other than minimal, and the consequences of failure can be hugely detrimental to DOD and the warfighter. This is especially true in IT service and solution bids.

Finally, in every technical services or solution bid, increased performance generally provides additional value to the government, and the government should strive to achieve an innovative, cost-effective solution to meet mission needs and maintain our technological advantage.

When LPTA is appropriate

LPTA procurements are appropriate for non-technical services or commodity bids and are an effective way of driving down these costs. In these instances, the LPTA source selection process can provide best value when combined with effective competition and proper contract type.

In his presentation at a Bloomberg Government event on March 12, Kendall gave an example of a service bid that in his opinion met the four tests. Lawn mowing services are a good example, he said, of the type of services where LPTA would be appropriate. In lawn mowing, the requirements are well defined, the risk of unsuccessful performance is minimal, additional value is not gained from higher performance than specified, and price is appropriately a significant factor in the selection.

This kind of procurement is the antithesis of where we have seen DOD use LPTA as its source selection process. Hopefully, this example will make it unambiguously clear that LPTA and technical service and solution bids don’t mix.

Why LPTA became popular

LPTA as a source selection process became popular with procurement officials for all the wrong reasons. First, it was an overreaction to budget reductions brought about by sequestration and budget caps. In austere times, procurement officials overemphasized the importance of cost in the source selection process—often to the detriment of technical performance. What we have learned is that overemphasizing cost causes bidders to be much more aggressive at risk taking, and bidders will understate their cost of performance in an effort to be the lowest priced, technically acceptable bidder. In the long run, expected cost savings are erased by cost overruns, contract modifications, show cause letters, and even contract terminations.   More….

 

Read the full blog post at:  http://washingtontechnology.com/articles/2015/04/07/insights-lohfeld-end-of-lpta.aspx

 


 

 For help with Government Contracting: contact your nearest Procurement Technical Assistance Center (PTAC). Funded through Cooperative Agreements between the U.S. Department of Defense and state and local governments/institutions, PTACs provide free and low-cost assistance in virtually all areas of government contracting.