Comparing Filing a Claim Versus an REA

December 22, 2016

Should I File a Claim or an REA on my Government Contract?

Source: Fox Rothschild LLP, Nicholas T. Solosky, November 2, 2016

Government contractors are frequently faced with the situation where they are owed additional time or are entitled to damages from the government on a contract.  For example, the government might be responsible for delays to the project schedule.  Or it might direct changes to the contract that make it more expensive to perform.

There are generally two methods for the contractor to pursue recovery – (1) filing a Claim under the Contract Disputes Act or (2) submitting a request for equitable adjustment (REA) to the contracting officer.  There are pros and cons to both methods and Contractors should take the time to consider these options carefully before moving forward.

What is the Difference between a Claim and an REA?

Claims and REAs are very similar (but not identical) in both form and function.  The basic concept is that the contractor is owed time or money (or both) on a contract and is providing the government with a written request for compensation.  The well-drafted Claim or REA will include a basic summary of the contractor’s performance and an easy-to-understand explanation of why it is entitled to the damages sought. READ MORE….

Contact your nearest PTAC to learn about government contracting.

 

Keep up to date follow us on Twitter, LinkedIN or Facebook!


 For help with Government Contracting: contact your nearest Procurement Technical Assistance Center (PTAC). Funded through Cooperative Agreements between the U.S. Department of Defense and state and local governments/institutions, PTACs provide free and low-cost assistance in virtually all areas of government contracting.